Caltrain work will reduce Alma Street to one lane

Original post made on Aug 31, 2023

Drives should expect delays on Alma Street next week as Caltrain prepares to fix potholes around two south Palo Alto rail crossings in preparation for electrification of the train system.

Read the full story here Web Link posted Thursday, August 31, 2023, 9:43 AM

Comments (4)

Posted by Morgan
a resident of Meadow Park
on Aug 31, 2023 at 7:11 pm

Morgan is a registered user.

Can they go fix the potholes on El Camino when they are finished?


Posted by Mondoman
a resident of Green Acres
on Aug 31, 2023 at 8:39 pm

Mondoman is a registered user.

Earlier this year, electric train service was supposed to start in early 2024 iirc (after having been postponed from 2022 and 2023). If they're now saying 2025, their project management skills seem not to have improved. More evidence that Palo Alto grade separation projects should just be put on hold for another decade or more until we know if Caltrain runs will ever return to even the numbers of 2019.


Posted by Reality Check
a resident of another community
on Sep 1, 2023 at 11:41 am

Reality Check is a registered user.

@Mondoman: the anticipated electrification revenue service date has long held steady at late 2024 and has not (yet!) slipped again. While average weekday ridership is still down by about 70%, Caltrain is still running 104 trains per weekday — comparable to pre-pandemic. Also note that federal funding Caltrain received for electrification was predicated on increased train service.


Posted by Mondoman
a resident of Green Acres
on Sep 1, 2023 at 10:37 pm

Mondoman is a registered user.

@Reality Check
I thought the revenue service date was modified last December in the "re-benchmarking". In any case, you are right that the most recent online documents (from a few months ago) still show late 2024 revenue service, with a slightly reduced contingency cushion.

Based on the documents from June, it looks like the biggest risks to the schedule are the re-do of the short-circuit(?) test in late October, and the ability of the trainset manufacturer to actual deliver the trainsets in time early next year. Sounds like we should have pretty good ideas on both in November.

You're right that Caltrain will have to apply for federal approval to keep the funding while reducing the number of trains in the near future.


Don't miss out on the discussion!
Sign up to be notified of new comments on this topic.

Email:


Post a comment

Sorry, but further commenting on this topic has been closed.

Stay informed.

Get the day's top headlines from Palo Alto Online sent to your inbox in the Express newsletter.

Burning just one "old style" light bulb can cost $150 or more per year
By Sherry Listgarten | 12 comments | 3,006 views

Banning the public from PA City Hall
By Diana Diamond | 26 comments | 2,160 views

Pacifica’s first brewery closes its doors
By The Peninsula Foodist | 0 comments | 1,891 views

Holiday Fun in San Francisco- Take the Walking Tour for An Evening of Sparkle!
By Laura Stec | 9 comments | 1,468 views

Premiere! “I Do I Don’t: How to build a better marriage” – Here, a page/weekday
By Chandrama Anderson | 2 comments | 1,430 views

 

Palo Alto Weekly Holiday Fund

For the last 30 years, the Palo Alto Weekly Holiday Fund has given away almost $10 million to local nonprofits serving children and families. 100% of the funds go directly to local programs. It’s a great way to ensure your charitable donations are working at home.

DONATE TODAY