Undergrounding of utility cables...

Original post made by Kedar Doshi on Jun 5, 2006

Does anybody know what the current status of that project. A few months ago, I had read that the midtown neighborhood was going to be worked on this summer, but I havent seen any signs of that yet.

Comments (1)

Posted by Patrick Valath, a resident of Midtown
on Jun 5, 2006 at 3:56 pm

Undergrounding of utility cables

I am assuming that the project you are referring is Underground District No. 41. We (Palo Alto Utilities - Electric Engineering) are currently preparing the construction drawings which is expected to go out for bids in July/August. Once a contractor is selected and the contract is awarded, construction will begin. The tentative date for start of construction is late August.


If you were a member and logged in you could track comments from this story.

Post a comment

Posting an item on Town Square is simple and requires no registration. Just complete this form and hit "submit" and your topic will appear online. Please be respectful and truthful in your postings so Town Square will continue to be a thoughtful gathering place for sharing community information and opinion. All postings are subject to our TERMS OF USE, and may be deleted if deemed inappropriate by our staff.

We prefer that you use your real name, but you may use any "member" name you wish.

Name: *

Select your neighborhood or school community: * Not sure?

Comment: *

Verification code: *
Enter the verification code exactly as shown, using capital and lowercase letters, in the multi-colored box.

*Required Fields

Veggie Grill coming soon to Mountain View's San Antonio Center
By Elena Kadvany | 25 comments | 3,824 views

. . . Loved in Spite of Ourselves
By Chandrama Anderson | 0 comments | 1,667 views

The Dude Abides
By Laura Stec | 4 comments | 1,609 views

Passover Joke
By Paul Losch | 6 comments | 487 views

The Cinderella ride
By Sally Torbey | 0 comments | 274 views